University of Alabama at Birmingham

Birmingham, Alabama
North Wing AHU Replacement

Hattemer, Hornsby & Bailey (HHB) served as the Engineer of Record for the replacement of AHU-1, which serves the 7th Floor Surgery Suites. Project features included:

  • Construction of a new penthouse as a second floor to the existing penthouse.
  • New AHU’s installed inside new Penthouse. Installation of piping, ductwork and power completed prior to change-over.
  • Change-over occurred over a weekend to allow maximum 2-hour shutdown of unit (unit also served a portion of the Emergency Room)
  • 100% outside air system with new exhaust fan equipped with run around heat recover coil.